Full NEBB-certified Testing, Adjusting & Balancing across the air and water systems of a data centre in Indonesia, proven not at one design condition but across every operating scenario the client specified, including with part of the water distribution out of service.
A data centre in Indonesia needed its full air and water scope balanced and documented, across every air handling unit, terminal unit, fan and outlet on the air side, and every pump and balancing valve behind them on the water side.
The client did not ask for a single design-condition balance. The scope called for water flow verified across a range of operating scenarios, terminal airflow measured at more than one condition, and flow proven again with part of the water distribution out of service. In other words: prove the facility works, then prove it still works when the pipework does not.
Skud mobilised two teams under its NEBB-certified TAB methodology, working days and nights to documented procedures so that every reading, including every repeated one, stayed traceable and defensible.
The full air and water scope was balanced to the NEBB acceptance tolerance of ±10%, and held there across every scenario the client specified, including with part of the water distribution out of service. The facility was handed over with a NEBB-format certified TAB report covering all of it.
The equipment that did not perform on first test is worth saying out loud, because it is the whole argument for independent testing. Nothing on this project was hidden by a favourable reading or averaged into an acceptable total. Where a unit did not meet design, the data said so, it was corrected, and it was measured again until it did. A report that only ever contains passes is a report that was never really a test.