Skud Technical Case Study Data Centre TAB Indonesia
Case study · Data centre

Not everything passed the first time. Everything passed in the end.

Full NEBB-certified Testing, Adjusting & Balancing across the air and water systems of a data centre in Indonesia, proven not at one design condition but across every operating scenario the client specified, including with part of the water distribution out of service.

Data centre Indonesia TAB NEBB-certified
Project snapshotSKUD
SectorData centre
LocationIndonesia
ScopeAir side and water side, full facility
ServiceTesting, Adjusting & Balancing
StandardNEBB-certified TAB methodology
OutcomeEvery system and scenario within ±10%
Scope at a glance

Air side, water side, and every scenario behind them.

Air + water
Full facility scope, both sides, one balance
Every scenario
Flow verified at each operating condition specified, not just design
±10%
NEBB acceptance tolerance held across every system and scenario
Retested
Where equipment did not perform, it was corrected and measured again
The brief

Prove it at design. Then prove it at every scenario after that.

A data centre in Indonesia needed its full air and water scope balanced and documented, across every air handling unit, terminal unit, fan and outlet on the air side, and every pump and balancing valve behind them on the water side.

The client did not ask for a single design-condition balance. The scope called for water flow verified across a range of operating scenarios, terminal airflow measured at more than one condition, and flow proven again with part of the water distribution out of service. In other words: prove the facility works, then prove it still works when the pipework does not.

The challenge

Scale, scenarios, and a programme that would not move.

  • Scenario testing multiplies everything. Every flow verification and every balancing point is measured more than once, because each scenario is another full pass across the same equipment.
  • A tight programme with no room to absorb delay, which meant night shifts and two teams working the facility in parallel.
  • Not all equipment performed when it was first tested. Each instance had to be recorded, corrected, and measured again, and in some cases more than once.
  • Every retest had to hold across the scenarios already proven, because a correction that fixes one condition can move another.
Our approach

Test, record, correct, test again.

Skud mobilised two teams under its NEBB-certified TAB methodology, working days and nights to documented procedures so that every reading, including every repeated one, stayed traceable and defensible.

  • Performance testing and air balancing across every air handling unit, terminal unit, and fan on the facility.
  • Pump performance testing, and flow verification and balancing at the valves both near the pumps and on the main pipe.
  • Water flow verified across every operating scenario specified, terminal airflow at more than one condition, and flow proven again with part of the water distribution out of service.
  • Independent readings throughout. Skud did not install, supply, or commission any of what it measured, so equipment that did not perform was reported as it measured.
The outcome

Every system, every scenario, inside NEBB tolerance.

The full air and water scope was balanced to the NEBB acceptance tolerance of ±10%, and held there across every scenario the client specified, including with part of the water distribution out of service. The facility was handed over with a NEBB-format certified TAB report covering all of it.

The equipment that did not perform on first test is worth saying out loud, because it is the whole argument for independent testing. Nothing on this project was hidden by a favourable reading or averaged into an acceptable total. Where a unit did not meet design, the data said so, it was corrected, and it was measured again until it did. A report that only ever contains passes is a report that was never really a test.

Worked to ▸ NEBB Procedural Standard for TAB ▸ ASHRAE 111