Skud Technical Case Study Data Centre TAB Johor Malaysia
Case study · Data centre

Proven at N, N+1 and N+2, not just with everything running.

Full NEBB-certified Testing, Adjusting & Balancing across the air and water systems of a data centre campus in Johor, Malaysia, then verified again at each redundancy configuration. Every system balanced at first pass.

Data centre Johor, Malaysia TAB NEBB-certified
Project snapshotSKUD
SectorData centre campus
LocationJohor, Malaysia
ScopeAir side and water side, as one system
ServiceTesting, Adjusting & Balancing
StandardNEBB-certified TAB methodology
OutcomeBalanced at first pass, N to N+2
Scope at a glance

A full campus balance, air and water, in one mobilisation.

Air + water
Full campus scope, both sides, one balance
N to N+2
Every redundancy configuration verified, not just design condition
First pass
No re-balancing, no return visits, no deficiency loop
Independent
Skud did not install, supply, or commission any of it
The brief

A data centre campus where redundancy had to be measured, not assumed.

The campus was designed around redundant cooling plant. N is the capacity needed to carry the design load. N+1 holds one unit spare. N+2 holds two. The commercial promise of the building rests on those configurations behaving the way they were drawn, because a hall that only holds conditions with every unit running is not redundant. It is fully loaded.

So the scope was not simply to balance the systems to design. It was to balance them, then prove the flows again at each configuration, so that the redundancy on the drawing existed in the measurements too.

None of that is unusual for the sector. Every data centre Skud tests is proven across N, N+1 and N+2, because it is the bar data centre clients set and the only condition under which the redundancy claim means anything. The question on a campus this size is not whether to do it. It is whether you can land it without three rounds of rework.

The challenge

The same valves, answering to three different sets of conditions.

  • Redundancy changes the hydraulics. Take plant out of service and the remaining units pick up the load: system curves shift, pressure drops move, and flow redistributes.
  • A balance that satisfies one configuration does not automatically satisfy the next, so a setting that lands N can compromise N+2.
  • Air side and water side had to be treated as one system across the data halls, because in a data hall they fail as one.
  • Balancing sits near the end of the critical path, where a failed first pass becomes a second mobilisation and a programme conversation.
Our approach

NEBB-certified TAB, sequenced to land all three configurations.

Skud mobilised its NEBB-certified TAB methodology across the full campus scope, working to documented procedures so every reading was traceable and defensible.

  • Performance testing and balancing across every air handling unit and terminal unit serving the data halls.
  • Pressure and performance testing across every chilled water pump, with every balancing valve set and verified.
  • Flows verified at N, N+1 and N+2, so the designed redundancy is evidenced rather than taken on trust.
  • Independent readings throughout. Skud did not install, supply, or commission any of what it measured.
The outcome

Every system tested, adjusted, and balanced at first pass.

The full air and water scope was balanced to NEBB tolerances and held at every configuration from N through N+2. No re-balancing, no return visits, and no deficiency loop between Skud, the contractor, and the consultant.

That is worth being plain about, because it is not luck. A clean first pass is what a documented method and agreed tolerances buy you, and on a data centre programme it is the difference between TAB being a milestone and TAB being a problem. The campus was handed over with a NEBB-format certified TAB report: an independent, third-party record of performance that stood up for every stakeholder on the project.

Worked to ▸ NEBB Procedural Standard for TAB ▸ ASHRAE 111
Have a project like this?

Independent, NEBB-certified TAB for complex and mission-critical projects.