Full NEBB-certified Testing, Adjusting & Balancing across the air and water systems of a data centre campus in Johor, Malaysia, then verified again at each redundancy configuration. Every system balanced at first pass.
The campus was designed around redundant cooling plant. N is the capacity needed to carry the design load. N+1 holds one unit spare. N+2 holds two. The commercial promise of the building rests on those configurations behaving the way they were drawn, because a hall that only holds conditions with every unit running is not redundant. It is fully loaded.
So the scope was not simply to balance the systems to design. It was to balance them, then prove the flows again at each configuration, so that the redundancy on the drawing existed in the measurements too.
None of that is unusual for the sector. Every data centre Skud tests is proven across N, N+1 and N+2, because it is the bar data centre clients set and the only condition under which the redundancy claim means anything. The question on a campus this size is not whether to do it. It is whether you can land it without three rounds of rework.
Skud mobilised its NEBB-certified TAB methodology across the full campus scope, working to documented procedures so every reading was traceable and defensible.
The full air and water scope was balanced to NEBB tolerances and held at every configuration from N through N+2. No re-balancing, no return visits, and no deficiency loop between Skud, the contractor, and the consultant.
That is worth being plain about, because it is not luck. A clean first pass is what a documented method and agreed tolerances buy you, and on a data centre programme it is the difference between TAB being a milestone and TAB being a problem. The campus was handed over with a NEBB-format certified TAB report: an independent, third-party record of performance that stood up for every stakeholder on the project.