Full NEBB-certified Testing, Adjusting & Balancing across a fast-track data centre in Selangor, Malaysia, from the chiller plant down to the last outlet, run day and night in step with the client’s HVAC commissioning team.
A data centre in Selangor needed its full air and water scope balanced and documented: 5 air handling units, 75 fan coil units, 7 pre-cool fan coil units, 34 fans and 301 outlets on the air side, and 3 chillers, 3 pumps and 18 CRAH units on the water side.
The scope ran further than most balancing packages. It included performance testing the chillers themselves, verifying flow at the chiller plant, and verifying the chilled water temperature and pressure sensors at the plant. Alongside all of it, the client’s HVAC commissioning team was running its own programme on the same systems, on a fast-track schedule that had no float in it.
Skud worked hand in hand with the client’s HVAC commissioning team throughout, running its NEBB-certified TAB methodology to documented procedures so that every figure handed across was traceable and defensible.
The full air and water scope was balanced to NEBB tolerances and documented, from the chiller plant through the CRAH units and down to the last of the 301 outlets, and the facility was handed over with a NEBB-format certified TAB report.
Independence is often mistaken for distance. It is not. Skud does not install, supply, or commission the systems it measures, and that is exactly what makes the readings worth having. But a reading is only worth having if it reaches the people who need it when they need it. On a fast-track programme, the independent party who is easy to work alongside is worth more than the independent party who is merely correct.