Skud Technical Case Study Data Centre TAB Selangor Malaysia
Case study · Data centre

Independent does not mean working alone.

Full NEBB-certified Testing, Adjusting & Balancing across a fast-track data centre in Selangor, Malaysia, from the chiller plant down to the last outlet, run day and night in step with the client’s HVAC commissioning team.

Data centre Selangor, Malaysia TAB NEBB-certified
Project snapshotSKUD
SectorData centre
LocationSelangor, Malaysia
ScopeChiller plant to outlet, air and water
ServiceTesting, Adjusting & Balancing
ProgrammeFast track, day and night working
OutcomeDelivered inside the commissioning programme
Scope at a glance

From three chillers down to three hundred outlets.

3
Chillers performance tested
18
CRAH units water balanced
121
Air-side units performance tested and balanced
301
Outlets balanced
The brief

A fast-track build where balancing sat inside someone else’s programme.

A data centre in Selangor needed its full air and water scope balanced and documented: 5 air handling units, 75 fan coil units, 7 pre-cool fan coil units, 34 fans and 301 outlets on the air side, and 3 chillers, 3 pumps and 18 CRAH units on the water side.

The scope ran further than most balancing packages. It included performance testing the chillers themselves, verifying flow at the chiller plant, and verifying the chilled water temperature and pressure sensors at the plant. Alongside all of it, the client’s HVAC commissioning team was running its own programme on the same systems, on a fast-track schedule that had no float in it.

The challenge

Commissioning cannot prove what balancing has not finished.

  • TAB is a dependency inside a commissioning programme, not a stage beside it. Functional testing on a system that is not yet balanced proves very little, so the commissioning team’s sequence depended on when our numbers landed.
  • Two teams, one set of plant. Working alongside another party’s programme means sequencing to what they need next, not to what is convenient to measure next.
  • Fast track with no float, which meant working days and nights to keep the balancing ahead of the commissioning front.
  • The scope reached the instruments themselves. A commissioning team reads its sequences through the plant sensors, so those sensors had to be verified independently rather than trusted.
Our approach

One team, two shifts, one shared programme.

Skud worked hand in hand with the client’s HVAC commissioning team throughout, running its NEBB-certified TAB methodology to documented procedures so that every figure handed across was traceable and defensible.

  • Air system performance testing and airflow balancing across all 121 air-side units and 301 outlets, level by level.
  • Water balancing at the CRAH units, water flow verification at the chiller plant, and pump performance testing.
  • Chiller performance testing, and independent verification of the chilled water temperature and pressure sensors at the plant, so the commissioning team was reading instruments that had been checked rather than assumed.
  • Day and night working, sequenced to the commissioning programme rather than to our own convenience.
The outcome

Balanced, verified, and handed across at the pace the programme needed.

The full air and water scope was balanced to NEBB tolerances and documented, from the chiller plant through the CRAH units and down to the last of the 301 outlets, and the facility was handed over with a NEBB-format certified TAB report.

Independence is often mistaken for distance. It is not. Skud does not install, supply, or commission the systems it measures, and that is exactly what makes the readings worth having. But a reading is only worth having if it reaches the people who need it when they need it. On a fast-track programme, the independent party who is easy to work alongside is worth more than the independent party who is merely correct.

Worked to ▸ NEBB Procedural Standard for TAB ▸ ASHRAE 111