Skud Technical Case Study Hospital TAB CPT Selangor Malaysia
Case study · Healthcare

The building was balanced. The isolation rooms were certified.

A hospital in Selangor, Malaysia, balanced end to end under NEBB-certified TAB, with its positive and negative isolation rooms certified separately to the NEBB cleanroom procedural standard.

Healthcare Selangor, Malaysia TAB CPT NEBB-certified
Project snapshotSKUD
SectorHealthcare
LocationSelangor, Malaysia
ScopeWard accommodation, treatment areas, and plant
ServiceTAB and Cleanroom Performance Testing
StandardNEBB-certified in both disciplines
OutcomeBalanced as a building, certified as containment
Scope at a glance

One building, two disciplines, one accountable party.

TAB + CPT
Both disciplines, one independent party, one mobilisation
Both ways
Isolation rooms running positive and negative, each proven
NEBB cleanroom
Isolation rooms certified to the cleanroom procedural standard
Independent
Skud did not install, supply, or commission any of it
The brief

Rooms that had to work in opposite directions.

A hospital ward block needed its full HVAC scope balanced. Inside it, the isolation rooms needed something more than a balance. They needed certifying.

Isolation rooms run in two directions, and the tower had both. A positive room holds pressure outward, keeping the building out to protect a patient whose immune system cannot defend itself. A negative room holds pressure inward, keeping the room in to protect everyone else from what is inside it. Same corridor, same air handling plant, opposite requirements. Point one the wrong way and it does the reverse of its job, silently, with nothing visible to anyone in the building.

The challenge

A balanced building is the floor, not the ceiling.

  • Two disciplines on one building. The tower is a balancing job. An isolation room is a containment device, and NEBB certifies those against its cleanroom procedural standard, not against an airflow tolerance.
  • The two are coupled. Every isolation room borrows its differential from the corridor around it, so the building balance sets the baseline the containment depends on. A room cannot hold what the floor around it will not give.
  • Positive and negative rooms sit alongside each other, drawing on the same plant, pulling in opposite directions.
  • Each isolation room runs its own dedicated extract, so each one is an individual system to prove rather than a sample drawn from a group.
Our approach

Both certifications, from one independent party.

Skud holds NEBB certification in Testing, Adjusting & Balancing and in Cleanroom Performance Testing, so the building and the isolation rooms were proven under one mobilisation, by one accountable party, working to documented procedures throughout.

  • NEBB-certified TAB across every air handling unit, terminal unit, supply grille, and extract and ventilation fan in the building.
  • Cleanroom Performance Testing on every isolation room, tested to the NEBB procedural standard for certified testing of cleanrooms.
  • Each room proven individually against the direction it was designed to hold, positive or negative, rather than sampled as a group.
  • Independent readings throughout. Skud did not install, supply, or commission any of what it measured.
The outcome

Balanced as a building, certified as containment.

The building was balanced to NEBB tolerances across its full air scope and documented throughout. Every isolation room was certified to the NEBB cleanroom procedural standard, each proven against the direction it was designed to hold rather than assumed correct because the floor around it balanced.

Both were handed over as NEBB-format certified reports from a single independent party: one record covering the building the isolation rooms sit in, and the isolation rooms themselves, with no gap between the two for a question to fall into.

Worked to ▸ NEBB Procedural Standard for TAB ▸ NEBB Procedural Standard for Certified Testing of Cleanrooms ▸ ASHRAE 111