Site Acceptance Testing of exhaust fans at a medical device manufacturing facility in Penang, Malaysia, where independent mechanical testing caught fans running in reverse and past vibration limit, and put them right with the installer before the site accepted them.
A medical device manufacturing facility in Penang needed Site Acceptance Testing of its exhaust fans: independent mechanical verification that each fan performed to specification before the site formally accepted the installation. A Site Acceptance Test is the gate between "installed" and "accepted," and once a site signs, the fan and its faults belong to the operator.
Skud was engaged to carry out that testing independently. Because Skud does not supply or install the equipment it tests, the acceptance record answers only to the measurements.
The testing found a number of exhaust fans running in reverse, and others vibrating past their acceptable limit. Both are exactly the kind of fault a Site Acceptance Test exists to catch, and both are the kind that quietly survive to handover if nobody independent puts an instrument on each fan.
Rather than simply log the faults, Skud worked alongside the installer to correct them: rotation reversed and set right, vibration brought back within limit, and every affected fan then retested and proven good. The site accepted an installation that had been independently verified, corrected where needed, and documented, with the faults resolved before acceptance rather than discovered after it.
A Site Acceptance Test that passes everything is not protecting anyone. This one earned its place: it caught faults that were real, mechanical, and easy to miss, and it caught them at the one moment they were still cheap to fix, before the site signed and the problem became the operator's to live with. That is the case for independent acceptance testing in a sentence.