Commissioning · The difference

Commissioning vs TAB: what is the difference?

Commissioning and Testing, Adjusting & Balancing are quoted almost interchangeably on drawings and tenders, but they are different scopes answering different questions. This guide sets out what each one covers, how they depend on each other, and where each sits in a project.

By Skud Technical· 8 min read· Updated August 2026
The short version
  • TAB is a specialist measurement discipline: it drives air and water flows to design and certifies them. Commissioning is the broad process of proving the whole building system performs as intended.
  • TAB sits inside commissioning. Commissioning relies on the TAB report as evidence, but adds controls, sequences, integration, and documentation on top.
  • They are not interchangeable and one does not replace the other. A project needs both, and the TAB result feeds the commissioning verification.
  • “Testing and commissioning” done by the installer is not the same as independent commissioning management, which verifies the process rather than delivering it.

Ask two people on a project what “commissioning” covers and you will often get two answers, one meaning the whole verification process and the other meaning the contractor’s own testing at the end of the job. The same slippage happens with TAB, which is sometimes treated as a synonym for commissioning and sometimes as a box already ticked by the installer. The distinction matters, because the two are separate scopes with separate deliverables, and confusing them is how a handover stalls.

The one-line answer: TAB proves the air and water flows are right; commissioning proves the whole system works as designed. Everything below unpacks that, and shows how the two fit together rather than compete.

What TAB is

Testing, Adjusting and Balancing is the specialist discipline of measuring, adjusting, and documenting that every air and water system delivers its designed flow, pressure, and temperature within tolerance. It is a measurement-and-adjustment scope with a defined method and a certified output: the TAB report. On critical projects it is carried out to the National Environmental Balancing Bureau (NEBB) Procedural Standard for TAB. It answers a narrow, essential question: are the flows right? For the detail of that scope, see testing, adjusting and balancing.

What commissioning is

Commissioning is the broad, managed process of verifying that a building’s systems perform as the design intended, not just individually but together. It reaches beyond flow into controls, sequences of operation, interlocks, integration between systems, and the documentation that proves it all. Where TAB asks whether the flows are right, commissioning asks whether the building actually behaves the way it was designed to across every operating mode. That work sits within commissioning management.

How they relate

The cleanest way to hold the two in mind: TAB is a discipline inside commissioning, and commissioning depends on it. A commissioning process cannot confirm a system performs to design if the air and water flows underneath it were never proven, so the TAB report is one of the evidence documents commissioning draws on. TAB is a component; commissioning is the umbrella. They are complementary, not alternatives.

TAB and commissioning, side by side
AspectTABCommissioning
Question answeredAre the air and water flows right?Does the whole system perform as designed?
ScopeFlow, pressure, temperature at terminals and equipmentControls, sequences, integration, documentation across systems
NatureSpecialist measurement and adjustmentManaged verification process
ReferenceNEBB Procedural Standard for TABASHRAE and CIBSE commissioning process frameworks (worked to)
DeliverableCertified TAB reportCommissioning report, incorporating the TAB data
TimingSystems installed, energised, controls functionalSpans design intent through to handover
The two overlap in the field but produce distinct documents. The TAB report is a defined technical certificate; the commissioning output is a wider verification record that draws the TAB report into it.

Where each sits in the programme

Commissioning is not a task at the end of a job; the process spans it, from confirming the design intent early, through installation, to final verification at handover. TAB is a defined activity later in that sequence: it runs once systems are installed, energised, and controls are functional, but it needs enough runway before handover to act on what it finds. Because commissioning draws on the TAB results, TAB should be programmed to complete before final commissioning sign-off, not squeezed into the last week alongside it.

▸ TAB proves the flows are right. Commissioning proves the building behaves the way it was designed to. You need the first before you can finish the second.

“Testing and commissioning” is not the same as commissioning management

A common source of confusion is the phrase “testing and commissioning,” often abbreviated to T&C, which on many projects refers to the installing contractor demonstrating that the plant they fitted runs. That is a normal and necessary part of construction. It is a different thing from independent commissioning management, where a third party manages and verifies the commissioning process across the whole building and confirms the evidence stands up. The installer’s testing answers “does my plant run?”; independent commissioning management answers “does the whole system perform as the design intended, and can we prove it?” Both have a place, and the independent role completes the picture for the design team, the client, and the authority signing off.

Why the independent view matters

Third-party TAB and commissioning give every stakeholder a single, defensible source of truth. When the party that installed a system also certifies its own performance, the data carries a conflict of interest that consultants and authorities increasingly will not accept. An independent report answers to the measurements, not to a programme deadline, which is exactly what makes it acceptable at handover. This completes the handover pack for everyone on the project rather than adding a hurdle to it.

What Skud provides

Skud Technical delivers both, as independent scopes. TAB is carried out to the NEBB Procedural Standard and certified in a TAB report; Skud is Malaysia’s only firm certified by the National Environmental Balancing Bureau (NEBB) in both TAB and Cleanroom Performance Testing. Commissioning management is delivered as a full independent scope, worked to the recognised commissioning process frameworks, ASHRAE Guideline 0 and Standard 202, and the CIBSE Commissioning Codes, and drawing the TAB evidence into a single verification record. The result is a handover pack the design team and authority can sign against with confidence.

Frequently asked questions

Is TAB part of commissioning?
Yes. TAB is a specialist measurement discipline that sits inside the broader commissioning process. Commissioning verifies that a whole building system performs as intended across controls, sequences, and integration, and it relies on the TAB report as evidence that air and water flows meet design. TAB is one input to commissioning, not a substitute for it.
What is the difference between testing and commissioning?
Testing measures whether individual elements meet their targets, for example whether a diffuser delivers its design airflow. Commissioning is the wider, managed process of proving that all the systems work together as the design intended, including controls, sequences, interlocks, and documentation. Testing produces data points; commissioning uses that data to confirm the building performs as a whole.
Does commissioning replace TAB?
No. The two answer different questions and produce different deliverables. TAB drives air and water flows to design and certifies them in a TAB report. Commissioning verifies whole-system performance and integration, and incorporates the TAB report as part of its evidence. A project needs both; one does not remove the need for the other.
When should TAB and commissioning happen in a project?
Commissioning spans the project, from confirming design intent early through to handover. TAB runs later, once systems are installed, energised, and controls are functional, but with enough time before handover to act on findings. The TAB results then feed the commissioning verification, so TAB should complete before final commissioning sign-off.