Fan wall units in data centres: how they work and how they are tested.
What a fan wall unit is, how it compares with CRAH and CRAC units, what goes wrong when it is not tested, and how fan walls are balanced and proven before a data hall goes live.
- A fan wall unit is a chilled water air handler with an array of many small EC fans, set in a gallery beside the data hall.
- It moves a large volume of air at low speed, saves white space floor area and builds redundancy into every unit.
- Uneven airflow, unbalanced coils and unproven failure response cause hot spots even when the BMS shows green.
- Testing, Adjusting & Balancing proves airflow, water flow, controls and redundancy before the hall goes live.
A fan wall unit is a cooling air handler built around an array of many small fans, usually EC (electronically commutated) plug fans, arranged in a grid across the face of a cooling coil. Instead of a few large units inside the data hall, a fan wall sits in a service corridor beside it and pushes a large volume of cool air across the room at low speed.
Fan walls have become a common choice for new hyperscale and colocation data centres, including the data center campuses now going up in Johor and Selangor. They save floor space in the white space, keep maintenance staff out of the data hall, and build redundancy into every unit. But a fan wall only delivers that performance if its airflow, water flow and controls are proven on site.
How a fan wall unit works
Warm air from the hot aisles returns to the fan wall gallery. It passes through a chilled water coil, and the fan array pushes the cooled air back into the data hall, usually at floor level and without a raised floor. Cold aisle or hot aisle containment keeps the two air streams apart.
The fans speed up and slow down together, controlled by the building management system (BMS). Most fan walls control on the pressure difference between the cold aisle and the hot aisle, so the fans supply just enough air for the IT load at that moment. The chilled water valve controls the supply air temperature.
Because the airflow is spread across many fans, losing one fan barely matters. The remaining fans ramp up to cover it, and the failed fan can be replaced while the unit keeps running.
Fan wall vs CRAH and CRAC units
| Feature | Fan wall unit | CRAH unit | CRAC unit |
|---|---|---|---|
| Cooling source | Chilled water coil | Chilled water coil | Direct expansion (refrigerant) |
| Location | Service gallery beside the data hall | Inside the data hall, usually on the perimeter | Inside the data hall |
| Air delivery | Large volume at low velocity, often no raised floor | Usually through a raised floor | Usually through a raised floor |
| Fans | Array of many small EC fans | A few larger fans | A few larger fans |
| Redundancy | Built into each unit through the fan array | Spare units in the room | Spare units in the room |
| Maintenance | Outside the white space | Inside the white space | Inside the white space |
CRAH and CRAC units still suit smaller computer rooms and retrofits. Fan walls suit large, high-density halls where floor space and uptime are worth the most.
What goes wrong when a fan wall is not tested
A fan wall can start, run and show green on the BMS while the data hall is still at risk. The common problems:
- Uneven airflow across the array. Fans near obstructions or at the edges of the coil deliver less air, so parts of the hall are starved.
- Coil water flow out of balance. If the chilled water flow through each coil is wrong, supply air temperature varies from unit to unit.
- Pressure control in the wrong place. A differential pressure sensor in a poor position makes the fans hunt, overshoot or under-supply.
- Air bypassing the servers. Gaps in containment, open floor or blanking panels left out let cold air return without doing any cooling.
- Redundancy that has never been proven. Nobody knows whether the hall holds temperature when a fan, a unit or a chilled water valve fails, until it happens live.
Each of these shows up as hot spots at server inlets, wasted fan energy, or a cooling failure under full load.
How fan wall units are tested and balanced
Fan wall testing is Testing, Adjusting & Balancing applied to a data hall. Each step is measured with calibrated instruments and recorded against the design.
| Test | What it proves |
|---|---|
| Airflow per fan and per unit | Each fan delivers its share. Many EC plug fans have inlet pressure taps that give airflow directly, and the unit total is checked with a duct or face traverse. |
| Total airflow to the hall | The units together supply the design airflow for the IT load, with the right margin. |
| Static and differential pressure | Pressure across the coil, filters and fans is within design, and the cold aisle to hot aisle pressure holds at its set point. |
| Chilled water flow per coil | Water balancing sets each coil to its design flow, so supply air temperature is even across all units. |
| Fan speed against the BMS | The speed the BMS commands is the speed the fans run, and the readings on screen match the measured values. |
| Supply and return temperatures | Each unit delivers its design supply temperature and the coil achieves its design temperature difference. |
| Failure response | With a fan, a unit or a valve switched off, the remaining fans ramp up and the hall stays within its temperature limits. |
The methods behind the airflow readings are covered in our guide to airflow measurement methods.
Where fan wall testing sits in data centre commissioning
Data centres are commissioned in five levels, from factory testing to integrated systems testing. Our article on testing and commissioning explains each level. Fan walls are tested at three of them:
- Level 3, start-up: each unit is started, fan rotation and safeties are checked, and first readings are taken.
- Level 4, functional performance testing: airflow and water flow are balanced to design, controls are proven, and failure scenarios are tested unit by unit.
- Level 5, integrated systems testing (IST): heat load banks stand in for the IT load. The whole hall is run at design load, power and chilled water failures are simulated, and temperatures are logged at the server inlets. ASHRAE recommends 18 to 27°C at the inlet for most IT equipment.
Before the hall goes live, many operators also run a particle count to confirm the white space is clean enough for IT equipment.
Why independent testing matters on a data centre
When the company that supplies or installs the fan walls also reports their performance, nobody checks the checker. A NEBB-certified TAB firm that does not install the systems it tests measures every fan and coil against the design, so the consultant and owner get data they can accept with confidence. Skud Technical provides NEBB-certified Testing, Adjusting & Balancing and commissioning support for data centre HVAC systems.
Fan wall units, answered plainly
What is a fan wall unit in a data center?
What is the difference between a fan wall and a CRAH unit?
Why do fan walls use EC fans?
How is fan wall redundancy tested?
Do fan walls need Testing, Adjusting & Balancing?
Building or upgrading a data hall with fan walls?
Skud Technical tests and balances fan wall units, chilled water systems and data hall airflow, and supports HVAC commissioning through to integrated systems testing. We work across Malaysia, including Sabah and Sarawak, as well as Singapore and the wider Asia region. Send us your scope and we will return a fixed proposal within 24 hours.